  25.       
Meeting Date: 09/17/2013  
10WC823 Hero Way Change Order No 12
Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  
Agenda Category: Regular Agenda Items

Information
Agenda Item
Consider approving Change Order No. 12 in the amount of -$56,510.80 for Hero Way, a Road Bond Project in Precinct Two.
Background
This Change Order provides for balancing the overrun / underrun Contract quantities for the project as a result of addressing field conditions not accounted for in the original plan quantities.  This Change Order also adds a new Contract item to assess liquidated damages for achieving Substantial Completion on February 15, 2013.  Substantial Completion was due on January 21, 2013; 365 days after time charges began on January 23, 2012.  Special Provision 000-1493 of the Contract specifies a liquidated damages amount of $800.00 per day for contracts more than $2,000,000 but less than $5,000,000.


Fiscal Impact
From/To Acct No. Description Amount
Attachments
Hero Way CO 12
Change Order 12 for Hero Way

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 09/12/2013 03:51 PM
Form Started By: kzaleski Started On: 09/12/2013 11:25 AM
Final Approval Date: 09/12/2013

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.