Commissioners Court - Regular Session


Issue viewing agenda items? Click here to switch to the old format.

Print

Return to the Minutes Page
  42.       
Meeting Date: 09/11/2012  
10WC821 Second Street Roadway Improvements Change Order No 6
Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  
Agenda Category: Regular Agenda Items

Information
Agenda Item
Consider approving Change Order No. 6 in the amount of $99,966.85 for Second Street Roadway Improvements, a Road Bond Project in Precinct Four.
Background
The City of Taylor has requested the Contractor to install additional waterlines and fittings, install additional wastewater lines and materials, and core manholes for additional wastewater services not included in the plans. This additional utility work will be added to the portion of the Contract reimbursed by the City.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
Second Street CO 6
Change Order 6 for Second Street Roadway Improvements

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 09/06/2012 10:37 AM
Form Started By: kzaleski Started On: 09/06/2012 08:31 AM
Final Approval Date: 09/06/2012

    