  26.       
Meeting Date: 08/11/2015  
12IFB00036 RM 620 Safety Improvements Change Order No 6
Submitted By: Dawn Haggard, Road Bond
Department: Road Bond  
Agenda Category: Regular Agenda Items

Information
Agenda Item
Discuss, consider and take appropriate action regarding Change Order No. 6 in the amount of $103,537.20 for RM 620 Safety Improvements, a Road Bond Project in Commissioner Pct. 1.
Background
This Change Order provides for the balancing of the overrun/underrun of Contract quantities for the project as a result of addressing field condition not accounted for in the original plan quantities and adds new Contract items for various work. The Change Order includes cost savings for underrunning flowable backfill, replacing concrete riprap with stone riprap in various locations, and utilizing existing conduit in lieu of new 2" and 3" conduit bores. Additional costs were added for a 36" storm sewer not quantified in the contract quantities, additional traffic control with peace officers for public safety, additional one-way signs in the median, adding new street names signs to the signal mast poles, and adding precast concrete islands to limit left turns. This Change Order also compensates the Contractor for the investigation to locate an existing Brushy Creek Municipal Utility District (BCMUD) waterline and for the installation of additional pipe for the connection to the existing waterline.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
RM 620 Safety CO 6
Change Order 6 for RM 620

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 08/06/2015 10:24 AM
Form Started By: Dawn Haggard Started On: 08/06/2015 09:31 AM
Final Approval Date: 08/06/2015

    