  27.       
Meeting Date: 08/16/2011  
09WC720 US 183 Change Order No 27
Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  
Agenda Category: Regular Agenda Items

Agenda Item
Consider approving Change Order No. 27 in the amount of $3,721.69 for US 183, a Pass Through Financing Project in Precinct Two.
Background
This Change Order compensates the Contractor for installation of a 12" waterline valve to a CTSUD waterline that was in conflict with the project grading. This allowed the abandonment of an unused portion of the waterline in conflict with the construction, so the contractor could remove it and continue work. CTSUD provided the 12" valve, but additional labor, equipment and materials were required for installation, shown here as a lump sum. It is anticipated that at a future time the County may need to replace the section of waterline that was removed.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
US 183 CO 27

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 08/10/2011 02:34 PM
Form Started By: kzaleski Started On: 08/10/2011 01:11 PM
Final Approval Date: 08/10/2011

    