  25.       
Meeting Date: 08/16/2011  
09WC720 US 183 Change Order No 25
Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  
Agenda Category: Regular Agenda Items

Agenda Item
Consider approving Change Order No. 25 in the amount of $17,325.00 for US 183, a Pass Through Financing Project in Precinct Two.
Background
This Change Order compensates the Contractor for the construction of Waterline I, which was not included in the original project plans. Waterline I is a portion of the existing 18-inch CTSUD waterline found to be in conflict with the drainage ditch in front of Water Quality Pond No. 3. This change order is in the amount of $17,325.00 and does not add or deduct any days to the contract time.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
US 183 CO 25
Change Order 25 for US 183

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 08/10/2011 02:34 PM
Form Started By: kzaleski Started On: 08/10/2011 12:59 PM
Final Approval Date: 08/10/2011

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.