25.
Meeting Date:
08/16/2011
09WC720 US 183 Change Order No 25
Submitted By:
Tiffany Mcconnell, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items
Agenda Item
Consider approving Change Order No. 25 in the amount of $17,325.00 for US 183, a Pass Through Financing Project in Precinct Two.
Background
This Change Order compensates the Contractor for the construction of Waterline I, which was not included in the original project plans. Waterline I is a portion of the existing 18-inch CTSUD waterline found to be in conflict with the drainage ditch in front of Water Quality Pond No. 3. This change order is in the amount of $17,325.00 and does not add or deduct any days to the contract time.
Fiscal Impact
From/To
Acct No.
Description
Amount
Attachments
US 183 CO 25
<
Form Review
Inbox
Reviewed By
Date
County Judge Exec Asst.
Wendy Coco
08/10/2011 02:34 PM
Form Started By:
kzaleski
Started On:
08/10/2011 12:59 PM
Final Approval Date:
08/10/2011
AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.