  30.       
Meeting Date: 08/02/2011  
10WC823 Hero Way Change Order No 3
Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  
Agenda Category: Regular Agenda Items

Agenda Item
Consider approving Change Order No. 3 in the amount of $16,661.05 for Hero Way, a Road Bond Project in Precinct Two.
Background
This Change Order adjusts the contract quantity of rip rap to match the designed quantity on the plans and summary sheet. This Change Order also provides a costs savings to change the storm sewer inlet standards to the TxDOT Austin District standards. The City of Leander concurs with the change in inlet standards. This change order is in the amount of $16,661.05 and does not add or deduct any days to the contract time.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
Hero Way CO 3

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 07/28/2011 09:50 AM
Form Started By: kzaleski Started On: 07/28/2011 09:38 AM
Final Approval Date: 07/28/2011

    