29.
Meeting Date:
07/10/2012
11WC916 SH 29 Intersection Improvements at Park Place and Jack Nicklaus Change Order No 2
Submitted By:
Tiffany Mcconnell, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items
Information
Agenda Item
Consider approving Change Order No. 2 in the amount of $1,277.23 for SH 29 Intersection Improvements at Park Place and Jack Nicklaus, a Road Bond Project in Precinct Three.
Background
This Change Order provides for payment of additional work by the Contractor to install block sod at Park Place in lieu of drill seeding, placing additional Ty C hot mix at the subdivision entrances on Jack Nicklaus and Park Place for a smooth tie-in, lengthening & installing additional rock berms to minimize erosion at the downstream ends of Culverts 1 and 3 at Park Place, and for restriping the entrance of Park Place. This Change Order also provides for balancing the overrun/underrun Contract quantities for the project as a result of addressing field conditions not accounted for in the original plan quantities.
Fiscal Impact
From/To
Acct No.
Description
Amount
Attachments
SH 29 Intersections CO 2
Change Order 2 for SH 29 at Park Place and Jack Nicklaus
<
Form Review
Inbox
Reviewed By
Date
County Judge Exec Asst.
Wendy Coco
07/05/2012 11:16 AM
Form Started By:
kzaleski
Started On:
07/05/2012 11:08 AM
Final Approval Date:
07/05/2012
AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.