Change Order ESOC - Vaughns
Submitted For:
Gary Wilson
Submitted By:
Connie Singleton, Purchasing
Department:
Purchasing
Agenda Category:
Regular Agenda Items
Information
Agenda Item
Discuss and take appropriate action on Change Order No. 14 in the amount of $398,427.00, which adds Division 27 – Telecom scope of work to Vaughn Construction’s scope of work for the ESOC Project.
Background
This Change Order is to add Telecom (Div 27) Scope of Work to Vaughn’s contract, as noted in Parsons Proposal Request #006, dated 4-25-12. Vaughn’s Best Value Recommendation is noted in the attached documents. This change will increase the current total GMP contract amount by $398,427. Additional GCs, Fee and days are included per allowable rates.
Fiscal Impact
From/To
Acct No.
Description
Amount
Attachments
Change Order 14 Vaughn ESOC
Change Order 14 for ESOC Project
<
Form Review
Inbox
Reviewed By
Date
Purchasing
rspace
07/05/2012 11:06 AM
County Judge Exec Asst.
Wendy Coco
07/05/2012 11:16 AM
Form Started By:
csingleton
Started On:
06/26/2012 10:18 AM
Final Approval Date:
07/05/2012