Meeting Date: 07/26/2011  
10WC812 CR 104 Phase 2 Change Order No 4
Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  
Agenda Category: Regular Agenda Items

Information
Agenda Item
Consider approving Change Order No. 4 in the amount of $17,706.17 for CR 104 Phase 2, a Road Bond Project in Precinct Three.
Background
This Change Order provides payment to the contractor for additional work requested by the County and TxDOT to minimize future maintenance. The additional work includes TxDOT requested soil retention blankets installed at the Mankins Branch Bridge in order to protect the slopes from erosion, redesign of the ditch in front of the Schroeder property, and use of 18" stone riprap in lieu of 12" stone riprap to create more stable slopes along the creeks.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
CR 104 Ph 2 CO 4
Change Order 4 for CR 104

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 07/21/2011 10:08 AM
Form Started By: kzaleski Started On: 07/21/2011 09:29 AM
Final Approval Date: 07/21/2011

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.