  23.       
Meeting Date: 07/19/2011  
Submitted For: Tiffany Mcconnell Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  

Information
Agenda Item
Consider approving Change Order No. 6 in the amount of $0.00 for BUS 79 Drainage (Project No. 09WC712), a Road Bond Project in Precinct Four.
Background
This change order extends the duration of the contract and provides additional contract days needed to complete additional work that was added to the contract with previous Change Order #4 (installation of culverts using hand digging). Change Order #4 was executed without a change to the contract time, to allow subsequent evaluation of the impact the new method of construction would have on the schedule. Based on the project progress to date, and the contractor’s anticipated schedule, 247 days are being added to the contract.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
09WC712 CO 6
BUS 79 Drainage Change Order 6

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 07/15/2011 03:36 PM
Form Started By: kzaleski Started On: 07/14/2011 11:24 AM
Final Approval Date: 07/15/2011

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.