24.
Meeting Date:
07/19/2011
Submitted For:
Tiffany Mcconnell
Submitted By:
Tiffany Mcconnell, Road Bond
Department:
Road Bond
Information
Agenda Item
Consider approving Change Order No. 19 in the amount of $20,376.08 for US 79 Section 5A (Project No. 08WC619), a Pass Through Financing project in Precinct Four.
Background
This change order revises contract quantities to document TxDOT requested changes to signing and striping, including striping of the area beyond the western project limits and shifting an overhead sign to more clearly define the lane exiting westbound to the Taylor loop. This change order also allows for the construction of an additional curb ramp and drainage inlet due to differing site conditions.
Fiscal Impact
From/To
Acct No.
Description
Amount
Attachments
08WC619 CO 19
<
Form Review
Inbox
Reviewed By
Date
County Judge Exec Asst.
Wendy Coco
07/14/2011 09:48 AM
Form Started By:
kzaleski
Started On:
07/13/2011 01:55 PM
Final Approval Date:
07/14/2011
AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.