Agenda Item
Discuss and consider approving Change Order No. 1 in the amount of $32,550.00 for Ronald Reagan Blvd. North Phase III (Project No. 11WC902), a Road Bond Project in Precinct Three.
Background
This change order adds to the contract a CTSUD 6” waterline that crosses the Ronald Reagan North Extension near CR 245, per the request of Chisholm Trail Special Utility District. The 6” waterline crossing of the Reagan North Extension near CR 245 will be encased in a 16” steel encasement pipe.
Fiscal Impact
From/To
Acct No.
Description
Amount
Attachments
11WC902 RRNIII CO 1
Ronald Reagan Blvd Phase III Change Order 1
<
Form Review
Inbox
Reviewed By
Date
County Judge Exec Asst.
Wendy Coco
07/07/2011 09:38 AM
Form Started By:
kzaleski
Started On:
07/06/2011 02:43 PM
Final Approval Date:
07/07/2011
AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.