Commissioners Court - Regular Session
Issue viewing agenda items? Click here to switch to the old format.
Print
Return to the Minutes Page
33.
Meeting Date:
07/12/2011
Submitted For:
Tiffany Mcconnell
Submitted By:
Tiffany Mcconnell, Road Bond
Department:
Road Bond
Information
Agenda Item
Discuss and consider approving Change Order No. 3 in the amount of $7,431.85 for CR 104 Phase 2 (Project No. 10WC812), a Road Bond Project in Precinct Three.
Background
The original plans did not include construction details for the sidewalk that extended beyond the approach slabs at the Mankins Branch Bridge. This Change Order provides these details. In addition to adding additional quantities for concrete flume and concrete curb and gutter, this Change Order adds three new pay items to the contract in order to reimburse the contractor for this work.
Also, TxDOT requested that one core hole per bridge bent be drilled in order to confirm that the drilled shaft foundations for the bridges were founded in solid material. This Change Order adds a pay item to the contract in order to provide payment to the contractor for this work.
Fiscal Impact
From/To
Acct No.
Description
Amount
Attachments
10WC812 CR 104 Ph 2 CO 3
CR 104 Phase 2 Change Order 3
<
Form Review
Inbox
Reviewed By
Date
County Judge Exec Asst.
Wendy Coco
07/07/2011 09:38 AM
Form Started By:
kzaleski
Started On:
07/06/2011 02:34 PM
Final Approval Date:
07/07/2011
AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.