  19.       
Meeting Date: 06/15/2010  
Submitted By: Krista Zaleski, Road Bond
Department: Road Bond  

Information
Agenda Item
Consider approving Change Order No. 19 in the amount of $64,437.41 for Pond Springs, a Road Bond Project in Precinct 1.
Background
The headwalls (heights) that were bid on for the project's three main culverts differ from the heights shown on the culvert layout sheets and what is required to meet field conditions. This change order covers the construction of the headwall's actual height at the upstream and downstream end of each culvert. In addition, to construct the new widened roadway over the southwest corner of Culvert #2, the upstream headwall had to be lengthened, which will require drilling piers and addtional traffic control.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
09WC710-CO#19
Pond Springs Change Order No 19

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 06/09/2010 03:09 PM
Form Started By: kzaleski Started On: 06/09/2010 11:34 AM
Final Approval Date: 06/09/2010

    