  14.       
Meeting Date: 05/24/2011  
Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  

Agenda Item
Consider approving Change Order No. 21 in the amount of $36,654.00 for US 183, a Pass Through Financing Project in Precinct Two.
Background
This change order is to compensate the contractor for work associated constructing Waterline J. Three hundred ninety feet (390 LF) of the existing 18-inch diameter waterline was found to be in conflict with the new ditchline between Structures 4 and 5 and had to be relocated.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
09WC720 US 183 CO21
US 183 CO21 Revised Plans

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 05/19/2011 11:02 AM
Form Started By: kzaleski Started On: 05/19/2011 10:42 AM
Final Approval Date: 05/19/2011

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.