Meeting Date: 05/24/2011  
Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  

Agenda Item
Consider approving Change Order No. 18 in the amount of $59,515.43 for US 79 Section 5A, a Pass Through Financing Project in Precinct Four.
Background
Contract Item 341 DENSE-GRADED HOT-MIX ASPHALT (QC/QA) requires the adjustment of compensation paid to the contractor based on the quality of the hot mix asphalt pavement produced and placed on the eastbound lanes. Specific job control tests were run on the asphalt (see attached back-up documentation) to monitor the quality of the mix. Using the results of these tests in conjunction with TxDOT formulas as outlined in the specifications, the Contractor was either awarded a bonus or assessed a penalty. This change order adds the pay item below to the contract in order to make the remainder of these pay adjustments that have not already been paid.

In addition, This Change Order includes the pay adjustment for the Ride Quality for the roadway pavement as required by Contract Item 585 RIDE QUALITY FOR PAVEMENT SURFACES. The pay adjustment is based on ride quality analyses completed with an inertial profiler (see attached back-up reports). This adjustment is made as it relates directly to the smoothness of the final pavement surface.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
08WC619 US 79 Sec 5A CO18
US 79 Sec 5A Backup
US 79 Sec 5A IRI Certification
Change Order 18 for US 79 Section 5A

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 05/19/2011 11:02 AM
Form Started By: kzaleski Started On: 05/19/2011 10:35 AM
Final Approval Date: 05/19/2011

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.