  18.       
Meeting Date: 05/10/2011  
Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  

Information
Agenda Item
Consider approving Change Order No. 17 in the amount of $86,291.48 for Williams Drive, a Road Bond Construction Project in Precinct Three.
Background
Contract Item 341 DENSE-GRADED HOT-MIX ASPHALT (QC/QA) requires the adjustment of compensation paid to the contractor based on the quality of the hot mix asphalt pavement produced and placed. Specific job control tests were run on the asphalt to monitor the quality of the asphalt mix. Using the results of these tests in conjunction with TxDOT formulas as outlined in the specification, the Contractor was either awarded a bonus or assessed a penalty. This change order adds pay items to the contract in order to make these pay adjustments.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
Change Orde 17
Change Order 17 for Williams Drive

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 05/05/2011 01:17 PM
Form Started By: kzaleski Started On: 05/05/2011 11:02 AM
Final Approval Date: 05/05/2011

    