Commissioners Court - Regular Session


Issue viewing agenda items? Click here to switch to the old format.

Print

Return to the Search Page Return to the Agenda
  23.       
Meeting Date: 04/02/2013  
10WC817 US 79 Section 3 Change Order No 20
Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  
Agenda Category: Regular Agenda Items

Information
Agenda Item
Consider approving Change Order No. 20 in the amount of -$78,475.90 for US 79 Section 3, a Pass-Through Financing project in Precinct Four.
Background
This Change Order provides for balancing the overrun / underrun Contract quantities for the project as a result of addressing field conditions not accounted for in the original plan quantities.  Also added are new Contract Items for an additional mowing cycle; railroad crossing striping; price adjustments for various types of asphalt; delays costs and liquidated damages.  This Change Order is a cost savings in the amount of -$78,475.90 and does not add any days to the Contract time.

Change Order No. 20 is the final Change Order for the three US 79 Pass Through Projects. For the total corridor, the original construction contracts totaled $48,508,294.44. As a result of cost savings measures discovered during construction and addressing final field conditions, the County has saved $412,146.72 (almost 1%), for a total corridor construction cost of $48,144,286.94 over the three projects.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
US 79 Section 3 CO 20

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 03/28/2013 12:57 PM
Form Started By: kzaleski Started On: 03/28/2013 09:48 AM
Final Approval Date: 03/28/2013

    