29.
Meeting Date:
03/18/2014
13IFB00118 CR 108 Change Order No 2
Submitted By:
Tiffany Mcconnell, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items
Information
Agenda Item
Consider approving Change Order No. 2 in the amount of $62,127.12 for CR 108, a Road Bond project in Precinct Four.
Background
This Change Order includes a cost sharing with City of Hutto to pay for half of the cost to adjust an existing City of Hutto waterline located directly underneath Culvert E. This Change Order also adds the adjustment of five fire hydrants and one wastewater manhole due to elevation changes around the existing facilities that occurred with the construction of the CR 108 improvements. The Change Order adds new Contract Items to provide for a driveway where the property owner previously accessed the property through the ditch. Also added are new Contract Items for a winter seed mix for vegetation establishment, an additional mobilization for the striping subcontractor to install additional raised pavement markers, and various items for cleanup of silt in the ditches due to the October 2013 storm event. In cooperation with the City of Taylor, this Change Order adds a new Contract Item for the cost for rehabilitation of 120 LF of the pavement section on Fowzer Street, which will be 50% reimbursed by the City of Taylor.
Fiscal Impact
From/To
Acct No.
Description
Amount
Attachments
CR 108 CO 2
Change Order 2 for CR 108
<
Form Review
Inbox
Reviewed By
Date
County Judge Exec Asst.
Wendy Coco
03/14/2014 08:38 AM
Form Started By:
kzaleski
Started On:
03/13/2014 11:52 AM
Final Approval Date:
03/14/2014
AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.