Commissioners Court - Regular Session


Issue viewing agenda items? Click here to switch to the old format.

Print

Return to the Minutes Page
  34.       
Meeting Date: 03/19/2013  
Sh 195 Project 2 - PEC Utility Agreement
Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  
Agenda Category: Regular Agenda Items

Information
Agenda Item
Discuss and take appropriate action regarding the Standard Utility Agreement with Pedernales Electric Cooperative (PEC) for utility relocation on the SH 195 Project and partial reimbursement of the relocations.
Background
PEC has existing facilities to be relocated to accommodate the roadway improvements, including relocation of 75 poles, more than 25,000 feet electric line and related appurtenances. The estimated reimbursable cost of the utility relocation is $1,152,835.82 (82.67% of the total $1,394,334.57 estimated cost). TxDOT has determined that PEC is 82.67% reimbursable and the determination letter is also attached.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
SH195-PEC-UtilityAgreement
SH195-PEC-Eligilibility
Pedernales Electric cooperative Standard Utility Agreement

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Peggy Vasquez 03/15/2013 11:05 AM
Form Started By: kzaleski Started On: 03/14/2013 06:53 AM
Final Approval Date: 03/15/2013

    