24.
Meeting Date:
03/20/2012
US 183 Change Order No 40
Submitted By:
Tiffany Mcconnell, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items
Information
Agenda Item
Consider approving Change Order No. 40 in the amount of $67,003.19 for US 183, a Pass Through Financing Project in Precinct Two.
Background
This Change Order provides for compensation to the Contractor for the work associated with the changes to the driveway pavements and associated drainage for added driveways and widened driveways at various locations due to ROW acquisitions. In addition, a few driveways were changed from a flex base & hot mix asphalt section to an asphalt overlay. This Change Order also provides for compensation to the Contractor for the widening, striping and drainage changes to River Run, which relocated the intersection with US 183 to the location of the River Run detour, a small cost savings to the project.
This Change Order is in the amount of $67,003.19 and does not add or deduct any days to the Contract time.
Fiscal Impact
From/To
Acct No.
Description
Amount
Attachments
US183-CO40
Change Order 40 for US 183
<
Form Review
Inbox
Reviewed By
Date
County Judge Exec Asst.
Peggy Vasquez
03/16/2012 01:39 PM
Form Started By:
kzaleski
Started On:
03/15/2012 07:38 AM
Final Approval Date:
03/16/2012