  34.       
Meeting Date: 03/22/2011  
Submitted For: Tiffany Mcconnell Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  

Information
Agenda Item
Discuss and consider approving Change Order No. 4 in the amount of $245,605.44 for US 79 Section 3, a Pass Through Financing project in Precinct Four.
Background
This change order compensates the contractor for safety end treatments which were not quantified in the bid items, not included in the original design, or were specified in the original design at the wrong size.

Additional change orders are under negotiation with the construction contractor and include (1) a reduction in contract cost for a reduced amount of concrete traffic barrier to be installed on the project and (2) a reduction in contract cost due to a change in the final asphalt surface course to PFC (the permeable surface that reduces spray and increases visibility during wet weather conditions), as preferred by TxDOT. The construction cost of the project is still within the overall project budget.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
10WC817-CO #4
US 79 Section 3 Change Order 4

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 03/17/2011 09:51 AM
Form Started By: kzaleski Started On: 03/17/2011 09:14 AM
Final Approval Date: 03/17/2011

    