11.
Meeting Date:
02/01/2011
Submitted For:
Tiffany Mcconnell
Submitted By:
Tiffany Mcconnell, Road Bond
Department:
Road Bond
Information
Agenda Item
Discuss and consider approving Change Order No. 12 in the amount of $235,322.81 for US 183, a Pass Through Financing Project in Precinct Two.
Background
This change order compensates the contractor for the work associated with the placement of hot mix asphalt concrete and embankment for temporary pavement on the project. The contract documents have no provisions for payment of construction of the required temporary pavement. These are plan items that were inadvertently omitted from the bid quantities by the design engineer, not additional work added after construction commenced.
Fiscal Impact
From/To
Acct No.
Description
Amount
Attachments
09WC720 - CO #12
<
Form Review
Inbox
Reviewed By
Date
County Judge Exec Asst.
Wendy Coco
01/27/2011 11:39 AM
Form Started By:
kzaleski
Started On:
01/27/2011 11:31 AM
Final Approval Date:
01/27/2011
AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.