  10.       
Meeting Date: 02/01/2011  
Submitted For: Tiffany Mcconnell Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  

Information
Agenda Item

Discuss and considering approving Change Order No. 7 in the amount of $56,647.61 for US 183, a Pass Through Financing Project in Precinct Two.

Background
This change order provides payment to reimburse the contractor for costs associated with addressing unanticipated soil conditions in Parcel 1.  The work items included consturction of a French drain, over-excavating the area and replacing the upper layer of high plasticity materials with low plasticity materials directly under the pavement section, and pumping water from the over-excavation of saturated clays until the French drain was in service.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
09WC720 - CO #7
09WC720 - CO #7 Backup

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 01/27/2011 11:39 AM
Form Started By: kzaleski Started On: 01/27/2011 11:24 AM
Final Approval Date: 01/27/2011

    