  23.       
Meeting Date: 02/03/2009  
Submitted For: Jim Rodgers Submitted By: Jim Rodgers, Parks
Department: Parks  

Information
Agenda Item
Consider approving Change Order # 2 for Chasco Constructors for Brushy Creek Regional Trail phase III in the amount $9,453.00
Background
Change order # 2 for Brushy Creek Trail phase III in the amount of $9,453 and is the close out document. This contract was not a lump sum contract but was based on actual items and measurements. Actual field measurements indicate that we needed more toe wall and less retaining wall resulting in the need for the change order. The attached change order document outlines the changes and drawings help demonstrate the item.  Funding would be suggested to come from 2006 park bonds as indicated in our park bond work session. 
The trail grand opening is scheduled for 10am March 7, 2009.   

Fiscal Impact
From/To Acct No. Description Amount
Attachments
BCRT III CO#2

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 01/29/2009 11:10 AM
Form Started By: jrodgers Started On: 01/28/2009 02:27 PM
Final Approval Date: 01/29/2009

    