40.
Meeting Date:
12/18/2012
10WC821 Second Street Roadway Improvements Change Order No 12
Submitted By:
Tiffany Mcconnell, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items
Information
Agenda Item
Consider approving Change Order No. 12 in the amount of $104,108.25 for Second Street Roadway Improvements, a Road Bond Project in Precinct Four.
Background
This Change Order adjusts the quantity of concrete pavement removal in the Contract
due to encountering a subsurface section of 6" unreinforced concrete pavement 68' wide by 1365' long inside the limits of the roadway excavation. The Change Order also adjusts the Contract quantities to account for an area shown on the plans as existing asphalt paving to be removed when in fact it was concrete paving.
Fiscal Impact
From/To
Acct No.
Description
Amount
Attachments
Second Street CO 12
<
Form Review
Inbox
Reviewed By
Date
County Judge Exec Asst.
Wendy Coco
12/13/2012 02:40 PM
Form Started By:
kzaleski
Started On:
12/11/2012 11:13 AM
Final Approval Date:
12/13/2012