36.
Meeting Date:
12/18/2012
10WC821 Second Street Roadway Improvements Change Order No 8
Submitted By:
Tiffany Mcconnell, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items
Information
Agenda Item
Consider approving Change Order No. 9 in the amount of $16,138.00 for Second Street Roadway Improvements, a Road Bond Project in Precinct Four.
Background
This Change Order adds new Contract Items and revises other existing Items to meet the City of Taylor’s request for additional drainage items and upsizing existing Contract items to eliminate flooding concerns for the Reese property located between Victoria Street and Howard Street on the north side of 2nd Street. The additional drainage facility (concrete lined ditch) up to the alley behind the Reese property and the cost of upsizing the drainage facilities will be reimbursed by the City of Taylor.
Fiscal Impact
From/To
Acct No.
Description
Amount
Attachments
Second St CO 8
Change Order 8 for Second Street in Taylor
<
Form Review
Inbox
Reviewed By
Date
County Judge Exec Asst.
Wendy Coco
12/13/2012 02:40 PM
Form Started By:
kzaleski
Started On:
12/11/2012 10:54 AM
Final Approval Date:
12/13/2012