13IFB00118 CR 108 Change Order No 3
Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  
Agenda Category: Regular Agenda Items

Information
Agenda Item
Consider approving Change Order No. 3 in the amount of $47,865.85 for County Road 108, a Road Bond Project in Precinct Four.
Background
This Change Order provides for a preliminary balancing of the overrun/underrun Contract quantities for the project as a result of addressing field conditions not accounted for in the original plan quantities and adds a new force account Contract item for water seepage investigations. This Change Order also adds new Contract items for the addition of rock gabion mattresses to be installed at the south end of the project near the US 79 intersection to serve as erosion control devices. The new items include compensation to the Contractor for grading the area, hauling off spoils, installing the mattresses, and cleanup of the adjacent area.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
CR 108 Change Order No 3

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 11/13/2014 01:41 PM
Form Started By: kzaleski Started On: 11/13/2014 11:09 AM
Final Approval Date: 11/13/2014

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.