  21.       
Meeting Date: 11/05/2013  
13IFB00108 IH 35 Northbound Frontage Road Change Order No 5
Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  
Agenda Category: Regular Agenda Items

Information
Agenda Item
Consider approving Change Order No. 5 in the amount of $146,697.00 for IH 35 Northbound Frontage Road, a Pass Through Financing project in Precinct Three.
Background
This Change Order adds new Contract Items for the installation of an 8-inch waterline to replace the existing City of Georgetown waterline in conflict with the south abutment of the new South San Gabriel River bridge at NBFR Sta. 227+15.  The waterline will be relocated in the TxDOT ROW from Sta. 228+82 to Sta. 242+38 along the edge of the ROW.  Change Order No. 5 deletes most of the items added previously by Change Order No. 3, which was processed simultaneously with the TxDOT permit for the Georgetown waterline to allow the Contractor to go to work once the permit was approved.  Change Order No. 5 reflects the final approved revisions to the waterline relocation plans and the specifications for the work are the same as was added previously.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
Change Order
Change Order 5 for IH 35 Northbound Frontage Road

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 10/31/2013 02:06 PM
Form Started By: kzaleski Started On: 10/31/2013 10:00 AM
Final Approval Date: 10/31/2013

    