  24.       
Meeting Date: 11/20/2012  
11WC915 SH 29 Two Way Left Turn Lane Change Order No 5
Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  
Agenda Category: Regular Agenda Items

Information
Agenda Item
Consider approving Change Order No. 5 in the amount of $10,274.00 for SH 29 Two-Way Left Turn Lane, a Road Bond Project in Precinct Two.
Background
This Change Order adds a driveway and driveway culvert at Sta 318+20 Left that was not evident in the field at the request of the property owner. This Change Order also revises the quantity for Reinforced Concrete Pipe (Arch)(Class 4)(Des 6) to match the amount of pipe needed in the field for the new Driveway at Sta 335+40 Left added by Change Order #3. The additional time added by this Change Order includes the time to procure & deliver materials and construct both additional driveways at Sta 318+20 and Sta 335+40.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
SH 29 TWLTL CO 5

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 11/15/2012 02:50 PM
Form Started By: kzaleski Started On: 11/15/2012 10:23 AM
Final Approval Date: 11/15/2012

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.