  16.       
Meeting Date: 10/13/2015  
Discuss, consider and take appropriate action on Change Order No.1, to contract with Adam Heath Construction in the amount of $3,600 for the sign shop
Submitted For: Terron Evertson Submitted By: Daribel Texidor, Unified Road System
Department: Unified Road System  
Agenda Category: Regular Agenda Items

Information
Agenda Item
Discuss, consider and take appropriate action on Change Order No. 1, to contract with Adam Heath Construction, fully executed on August 6, 2015, in the amount of $3,600.00 for sign shop renovations.
Background
This change order would be utilized to install partitions in the restrooms.  This project is nearly complete, with the change order and minor punch items remaining to be completed.  The Original Contract amount was $25,885.00, Change Order # 1 would increase the contract amount by $3,600.00, for an adjusted, Total Contract Amount of $29,485.00.  No additional days will be added to, or deducted from, the Contract as a result of this Change Order.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
Invoice
Contract
Change Order

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 10/08/2015 02:02 PM
Form Started By: Daribel Texidor Started On: 10/08/2015 10:51 AM
Final Approval Date: 10/08/2015

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.