11WC902 Ronald Reagan Boulevard North Phase III Change Order No 3
Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  
Agenda Category: Regular Agenda Items

Information
Agenda Item

Consider approving Change Order No. 3 in the amount of $75,804.00 for Ronald Reagan Boulevard North Phase III, a Road Bond Project in Precinct Three.

Background
This Change Order compensates the Contractor for installing fencing along the ROW where property was donated for the project (Madison). This Change Order also adds quantities to the Prep ROW, Excavation, Embankment, and Curb & Gutter Items in the Contract for the portion of the roadway north of SH 195; which were inadvertently omitted by the Engineer during the bidding process.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
Ronald Reagan North Ph III CO 3

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 10/19/2011 02:29 PM
Form Started By: kzaleski Started On: 10/19/2011 11:24 AM
Final Approval Date: 10/19/2011

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.