  19.       
Meeting Date: 10/18/2011  
10WC817 US 79 Section 3 Change Order No 10
Submitted By: Tiffany Mcconnell, Road Bond
Department: Road Bond  
Agenda Category: Regular Agenda Items

Information
Agenda Item

Consider approving Change Order No. 10 in the amount of $13,816.60 for US 79 Section 3, a Pass Through Financing Project in Precinct Four.

Background
This Change Order compensates the Contractor for changes to the wastewater line installed with this project and additional testing not in the original contract specifications requested by the City of Hutto. The requests include CCTV testing of the new wastewater line, lowering of the manhole at Sta. 1+00 for accessibility purposes, and vacuum testing of the existing manholes. These items are industry standard practices for the construction of wastewater lines, but were not included in the project specifications.

Fiscal Impact
From/To Acct No. Description Amount
Attachments
US 79 Sec 3 CO 10
Change Order 10 for US 79 Section 3

<
Form Review
Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 10/13/2011 08:44 AM
Form Started By: kzaleski Started On: 10/13/2011 08:27 AM
Final Approval Date: 10/13/2011

    